The Estimate Locking process is a critical important activity within the lifecycle of a contract/project. This Estimate Lockout process has the following actions and effects on the contract/project:

    • Progress Payment Estimate is generated
    • Pay Item usage for the period may no longer be changed
    • IDR data associated within the locked payment period is locked and may no longer be changed
    • IDRs for a locked pay period may not be created


Note: The lockout process does not affect Force Account Records (FARs).




Next Topic: Estimate Lockout Process