11.5 Estimate Lockout
The Estimate Locking process is a critical important activity within the lifecycle of a contract/project. This Estimate Lockout process has the following actions and effects on the contract/project:
- Progress Payment Estimate is generated
- Pay Item usage for the period may no longer be changed
- IDR data associated within the locked payment period is locked and may no longer be changed
- IDRs for a locked pay period may not be created
Note: The lockout process does not affect Force Account Records (FARs).
Next Topic: Estimate Lockout Process